[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150499,803,1,"单选题","根据《水利水电工程施工组织设计规范》，工程建设全过程可划分为工程筹建期、工程准备期、主体工程施工期和工程完建期四个施工时段。编制施工总进度时，工程施工总工期应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","主体工程施工期和工程完建期之和",false,{"key":16,"text":17,"correct":14},"B","工程筹建期和主体工程施工期之和",{"key":19,"text":20,"correct":21},"C","工程准备期、主体工程施工期和工程完建期之和",true,{"key":23,"text":24,"correct":14},"D","工程准备期和工程完建期之和","工程建设全过程可划分为工程筹建期、工程准备期、主体工程施工期和工程完建期四个施工时段。编制施工总进度时,工程施工总工期应为后三项工期之和。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]