[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150497,803,1,"单选题","水力发电工程截流验收、项目法人应在计划截流前（ ）个月，向省级人民政府能源主管部门报送工程截流验收申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","12","本题考查的是水力发电工程阶段验收的要求。水力发电工程截流验收、项目法人应在计划截流前6个月，向省级人民政府能源主管部门报送工程截流验收申请。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]