[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150487,803,1,"单选题","水利工程阶段验收的成果性文件是阶段验收鉴定书，自验收鉴定书通过之日起（ ）个工作日内，由验收主持单位发送有关单位。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","30",true,{"key":23,"text":24,"correct":14},"D","40","本题考查的是水利工程阶段验收的要求。水利工程阶段验收的成果性文件是阶段验收鉴定书，自验收鉴定书通过之日起30个工作日内，由验收主持单位发送有关单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]