[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150470,803,1,"单选题","根据《水电建设工程质量管理暂行办法》，监理单位对工程建设工程中的设计与施工质量负（ ）责任。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接",false,{"key":16,"text":17,"correct":14},"B","直接领导",{"key":19,"text":20,"correct":21},"C","监督与控制",true,{"key":23,"text":24,"correct":14},"D","领导与监督","本题考查的是水力发电工程建设各方职责。监理单位对工程建设过程中的设计与施工质量负监督与控制责任，对其验收合格项目的施工质量负直接责任。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]