[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150428,803,1,"单选题","在变更的估价原则中，已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由（ ）商定或确定变更工作的单价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人",true,{"key":16,"text":17,"correct":18},"B","发包人",false,{"key":20,"text":21,"correct":18},"C","设计人",{"key":23,"text":24,"correct":18},"D","承包人","本题考查的是施工合同管理。在变更的估价原则中，已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]