[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150424,803,1,"单选题","除专用合同条款另有约定外，施工控制网由承包人负责测设，发包人应在本合同协议书签订后的（ ）天内，向承包人提供测量基准点、基准线和水准点及其相关资料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","30","除专用合同条款另有约定外,施工控制网由承包人负责测设,发包人应在本合同协议书签订后的14 天内,向承包人提供测量基准点、基准线和水准点及其相关资料。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]