[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150417,803,1,"单选题","水利工程勘察设计评标一般采取综合评标法，具体评标方法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先评商务标，商务标评分占40%",false,{"key":16,"text":17,"correct":18},"B","先评技术标，技术标评分占40%",true,{"key":20,"text":21,"correct":14},"C","先评商务标，商务标评分占60%",{"key":23,"text":24,"correct":14},"D","先评技术标，技术标评分占60%","采用综合评标洼的,应先评技术标,再评商务标。评标时分别打分,然后按照技术标评分占40%权重、商务标评分占60%权重评定最终得分。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]