[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150410,803,1,"单选题","某施工单位承担一水电站工程项目施工，其中施工单位可以分包的工程项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","坝体填筑",false,{"key":16,"text":17,"correct":14},"B","大坝护坡",{"key":19,"text":20,"correct":14},"C","电站厂房",{"key":22,"text":23,"correct":24},"D","尾水渠护坡",true,"本题考查的是水利水电工程项目法人分包管理职责。水利建设工程的主要建筑物的主体结构不得进行工程分包。主要建筑物是指失事以后将造成下游灾害或严重影响工程功能和效益的建筑物，如堤坝、泄洪建筑物、输水建筑物、电站厂房和泵站等。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]