[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150402,803,1,"单选题","根据主体工程开工的有关规定，项目法人应当自工程开工之日起15工作日内将（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开工情况的书面报告上报上一级主管单位审批",false,{"key":16,"text":17,"correct":18},"B","开工情况的书面报告上报上一级主管单位备案",true,{"key":20,"text":21,"correct":14},"C","开工报告上报上一级主管单位备案",{"key":23,"text":24,"correct":14},"D","开工报告上报上一级主管单位审批","本题考查的是建设实施阶段的工作内容。水利工程具备开工条件后，主体工程方可开工建设。项目法人或建设单位应当自工程开工之日起15个工作日之内，将开工情况的书面报告报项目主管单位和上一级主管单位备案。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]