[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150400,803,1,"单选题","工程初步设计静态总投资宜控制在可行性研究报告相应估算静态总投资（ ）以下。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15%",false,{"key":16,"text":17,"correct":14},"B","25%",{"key":19,"text":20,"correct":21},"C","115%",true,{"key":23,"text":24,"correct":14},"D","125%","本题考查的是水利工程建设项目的类型及建设阶段划分。静态总投资超过可行性研究报告相应估算静态总投资15%以上（含15%）时，必须重新编制可行性研究报告并按原程序报批。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]