[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150385,803,1,"单选题","当水利工程建设项目初步设计静态总投资超过已批准的可行性研究报告估算静态总投资达10%时，则需（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提出专题分析报告",true,{"key":16,"text":17,"correct":18},"B","重新编制初步设计",false,{"key":20,"text":21,"correct":18},"C","调整可行性研究投资估算",{"key":23,"text":24,"correct":18},"D","重新编制可行性研究报告","概算静态总投资原则上不得突破已批准的可行性研究报告估算的静态总投资。由于工程项目基本条件发生变化，引起工程规模、工程标准、设计方案、工程量的改变，其静态总投资超过可行性研究报告相应估算静态总投资在15%以下时，要对工程变化内容和增加投资提出专题分析报告。超过15%以上（含15%）时，必须重新编制可行性研究报告并按原程序报批。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]