[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150381,803,1,"单选题","以下关于重大设计变更的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由项目法人确认",false,{"key":16,"text":17,"correct":14},"B","报项目主管部门核备",{"key":19,"text":20,"correct":14},"C","必要时报项目主管部门审批",{"key":22,"text":23,"correct":24},"D","报原初步设计审批部门审批",true,"重大设计变更文件，由项目法人按原报审程序报原初步设计审批部门审批。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]