[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150352,803,1,"单选题","下列施工放样的资料中，属于放样数据计算依据的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","放样数据手册",false,{"key":16,"text":17,"correct":14},"B","放样草图",{"key":19,"text":20,"correct":14},"C","放样手簿",{"key":22,"text":23,"correct":24},"D","设计图纸",true,"本题考查的是施工放样的基本工作。放样前应根据设计图纸和有关数据及使用的控制点成果，计算放样数据，绘制放样草图，所有数据、草图均应经两人独立计算与校核。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]