[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150297,803,1,"单选题","堤防横断面上的地面坡度陡于（ ）时，应将地面坡度削至缓于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1：2；1:2",false,{"key":16,"text":17,"correct":14},"B","1：3；1:3",{"key":19,"text":20,"correct":14},"C","1：4；1:4",{"key":22,"text":23,"correct":24},"D","1：5；1:5",true,"本题考查的是填筑作业面的要求。堤防横断面上的地面坡度陡于1：5时，应将地面坡度削至缓于1：5。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]