[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150218,803,1,"单选题","在帷幕灌浆施工中，当某一比级浆液的注入量已达300L以上或灌浆时间已达（ ）min时，而灌浆压力和注入率均无改变或改变不显著时，应改浓一级水胶比。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30",true,{"key":16,"text":17,"correct":18},"B","60",false,{"key":20,"text":21,"correct":18},"C","90",{"key":23,"text":24,"correct":18},"D","120","本题考查的是帷幕灌浆。在帷幕灌浆施工中，当某一比级浆液的注入量已达300L以上或灌浆时间已达30min时，而灌浆压力和注入率均无改变或改变不显著时，应改浓一级水胶比。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]