[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150199,803,1,"单选题","中型基坑初期排水，排水时间可采用（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3～5天",true,{"key":16,"text":17,"correct":18},"B","4～6天",false,{"key":20,"text":21,"correct":18},"C","5～7天",{"key":23,"text":24,"correct":18},"D","6～8天","本题考查的是初期排水。一般情况下，大型基坑可采用5～7d，中型计控可采用3～5d。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]