[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150187,803,1,"单选题","基坑初期排水流量Q=ηV\u002FT，其中V 代表（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","日平均降水量",false,{"key":16,"text":17,"correct":14},"B","初期排水总量",{"key":19,"text":20,"correct":21},"C","基坑积水体积",true,{"key":23,"text":24,"correct":14},"D","可能的降水总量","初期排水流量：Q=ηV\u002FT，Q——初期排水流量（m3\u002Fs），V——基坑的积水体积（m3）；T——初期排水时间（s）；η——经验系数，一般取η=3-6。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]