[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150178,803,1,"单选题","（2018年真题）根据《中华人民共和国水土保持法》下列关于水土保持设施与主体“三同时”的说法错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","同时设计",false,{"key":16,"text":17,"correct":14},"B","同时施工",{"key":19,"text":20,"correct":14},"C","同时投产使用",{"key":22,"text":23,"correct":24},"D","同时验收",true,"本题考查的是水土流失的治理要求。为保证经过批准的水土保持方案的严格实施，建设项目中的水土保持设施，必须与主体工程同时设计、同时施工、同时投产使用。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]