[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150164,803,1,"单选题","（2014年）根据《水电工程验收管理办法》（国能新能〔2011〕263号），水电工程截流验收由项目法人会同（ ）等单位共同组织进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目审批部门",false,{"key":16,"text":17,"correct":18},"B","省级能源主管部门",true,{"key":20,"text":21,"correct":14},"C","质监总站",{"key":23,"text":24,"correct":14},"D","电网经营管理单位","工程截流验收由项目法人会同省级发展改革委、能源主管部门共同组织验收委员会进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]