[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150158,803,1,"单选题","（2017年）根据《水利水电建设工程验收规程》SL223-2008，若工程建设项目不能按期进行竣工验收的，经竣工验收主持单位同意，可适当延长期限，最长可延期（ ）个月。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","3","根据《水利水电建设工程验收规程）） SL 223-2008 ，竣工验收应在工程建设项目全部完成并满足一定运行条件后1 年内进行。不能按期进行竣工验收的，经竣工验收主持单位同意，可适当延长期限，但最长不得超过6 个月。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]