[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150141,803,1,"单选题","（2009年）某水电站进水口边坡施工中发生质量事故，经调查，事故造成直接经济损失约20万元，处理后不影响工程正常使用和寿命。根据有关规定，该事故属于（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重大质量事故",false,{"key":16,"text":17,"correct":14},"B","较大质量事故",{"key":19,"text":20,"correct":21},"C","一般质量事故",true,{"key":23,"text":24,"correct":14},"D","质量缺陷","",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]