[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150134,803,1,"单选题","（2015年）根据《水利工程设计变更管理暂行办法》（水规计［2012］93号），涉及工程规模发生较大变化的设计变更应事先征得（）的同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原可行性研究报告批复部门",true,{"key":16,"text":17,"correct":18},"B","原初步设计审查部门",false,{"key":20,"text":21,"correct":18},"C","施工图设计审查部门",{"key":23,"text":24,"correct":18},"D","项目主管部门","涉及工程开发任务变化和工程规模、设计标准、总体布局等方面较大变化的设计变更，应当征得原可行性研究报告批复部门的同意。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]