[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150131,803,1,"单选题","（2019年真题）工程静态总投资超过可行性研究报告相应估算静态总投资()，必须重新编制可行性研究报告并按原程序报批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","10%",{"key":19,"text":20,"correct":14},"C","12%",{"key":22,"text":23,"correct":24},"D","15%",true,"P145-148 本题考查的是水利工程建设项目的类型及建设阶段划分。静态总投资超过可行性研究报告相应估算静态总投资在15%以下时，要对工程变化内容和增加投资提出专题分析报告。静态总投资超过可行性研究报告15%以上(含15%)时，必须重新编制可行性研究报告并按原程序报批。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]