[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150126,803,1,"单选题","（2018年真题）根据《水利基本建设项目竣工财务决算编制规程》（SL19-2014），大型项目进行竣工决算时，未完工程投资和预留费用的比例不得超过（）的3%。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总概算",true,{"key":16,"text":17,"correct":18},"B","总估算",false,{"key":20,"text":21,"correct":18},"C","预算总价",{"key":23,"text":24,"correct":18},"D","合同总价","本题考查的是水利工程建设稽察、决算与审计的内容。建设项目未完工程投资及预留费用可预计纳入竣工财务决算。大中型项目应控制在总概算的3%以内，小型项目应控制在5%以内。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]