[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150124,803,1,"单选题","（2017年）根据《关于水利工程建设项目代建制管理的指导意见》（水建管[2015]91号)，拟实施代建制的项目应在（ )阶段前选定代建单位。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工准备",true,{"key":16,"text":17,"correct":18},"B","开工建设",false,{"key":20,"text":21,"correct":18},"C","可行性研究报告",{"key":23,"text":24,"correct":18},"D","主体开工","拟实施代建制的项目应在可行性研究报告中提出实行代建制管理的方案，经批复后在施工准备前选定代建单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]