[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150117,803,1,"单选题","（2015年）根据《关于水利工程建设项目代建制管理的指导意见》（水建管〔2015〕91号），水利工程建设项目代建单位负责对水利工程建设项目（ ）的建设进行管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工准备至竣工验收",true,{"key":16,"text":17,"correct":18},"B","初步设计至竣工验收",false,{"key":20,"text":21,"correct":18},"C","可行性研究至竣工验收",{"key":23,"text":24,"correct":18},"D","可行性研究至后评价","根据《关于水利工程建设项目代建制管理的指导意见》（水建管〔2015〕91号），水利工程建设项目代建制为建设实施代建，代建单位对水利工程建设项目施工准备至竣工验收的建设实施过程进行管理。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]