[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150100,803,1,"单选题","（2016年）根据《堤防工程施工规范》（SL260-2014），填筑堤防横断面的地面坡度较陡，施工时应将地面坡度削至缓于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1:3",false,{"key":16,"text":17,"correct":14},"B","1:4",{"key":19,"text":20,"correct":21},"C","1:5",true,{"key":23,"text":24,"correct":14},"D","1:6","根据《堤防工程施工规范》（SL260-2014），地面起伏不平时，应按水平分层由低处开始逐层填筑，不得顺坡铺填；堤防横断面上的地面坡度陡于1:5时，应将地面坡度削至缓于1:5。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]