[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150078,803,1,"单选题","（2012年）面板堆石坝坝体分区从迎水面到背水面依次是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过渡区、垫层区、主堆石区、次堆石料区",false,{"key":16,"text":17,"correct":18},"B","垫层区、过渡区、主堆石区、次堆石料区",true,{"key":20,"text":21,"correct":14},"C","垫层区、过渡区、次堆石料区、主堆石料区",{"key":23,"text":24,"correct":14},"D","过渡区、垫层区、次堆石料区、主堆石料区","面板堆石坝坝体分区基本定型，主要有垫层区、过渡区、主堆石区、下游堆石区（次堆石料区）等。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]