[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150076,803,1,"单选题","（2006年）土石坝采用进退错距法施工，若施工工作面宽3.0m，碾压机械碾滚净宽1.5m，设计碾压遍数为5遍，则错距碾压宽度为（）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.3",true,{"key":16,"text":17,"correct":18},"B","0.5",false,{"key":20,"text":21,"correct":18},"C","0.6",{"key":23,"text":24,"correct":18},"D","2.0","",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]