[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150027":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150027,803,1,"单选题","（2010年）拱坝在校核洪水位承受的波浪压力属于（）作用荷载。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","永久",false,{"key":16,"text":17,"correct":14},"B","基本",{"key":19,"text":20,"correct":14},"C","可变",{"key":22,"text":23,"correct":24},"D","偶然",true,"根据《水工建筑物荷载设计规范》（SL 744—2016）， 永久荷载：建筑物结构自重、永久设备自重、地应力、围岩压力、土压力、预应力锚固荷载、淤沙压力（有排沙设施时可列为偶然荷载）； 可变荷载：静水压力、外水压力、扬压力、动水压力、风荷载、雪荷载、冰压力、冻胀力、浪压力、楼面活荷载、平台活荷载、桥机荷载、闸门启闭机荷载、温度荷载、灌浆荷载、土壤空隙水压力、系缆力、撞击力等； 偶然荷载：校核洪水时的静水压力、地震荷载等。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]