[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150004,803,1,"单选题","（2018年真题）下列观测方法中，适用于翼墙沉降观测的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","交会法",false,{"key":16,"text":17,"correct":14},"B","视准线法",{"key":19,"text":20,"correct":14},"C","小角度法",{"key":22,"text":23,"correct":24},"D","水准观测法",true,"本题考查的是施工期间的外部变形监测。一般情况下，滑坡、高边坡稳定检测采用交会法；水平位移监测采用视准线法（活动觇牌法和小角度法）；垂直位移观测，宜采用水准观测法，也可采用满足精度要求的光电测距三角高程法；地基回弹宜采用水准仪与悬挂钢尺相配合的观测方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]