[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1149993,803,1,"单选题","（2016年）下列施工放样的资料中，属于施工放样数据计算依据的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测量手册",false,{"key":16,"text":17,"correct":14},"B","测量手簿",{"key":19,"text":20,"correct":21},"C","控制点成果",true,{"key":23,"text":24,"correct":14},"D","测量数据","放样前应根据设计图纸和有关数据及使用的控制点成果，计算放样数据，绘制放样草图，所有数据、草图均应经两人独立计算与校核。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]