[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149988":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149988,802,2,"多选题","综合管廊模板施工前，应根据（）条件进行模板及支架设计。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","结构形式",true,{"key":16,"text":17,"correct":14},"B","施工工艺",{"key":19,"text":20,"correct":14},"C","设备",{"key":22,"text":23,"correct":14},"D","材料供应",{"key":25,"text":26,"correct":27},"E","政府管理部门要求",false,"ABCD","2020教材P469 \u002F 2019教材P470 (1) 综合管廊模板施工前，应根据结构形式、施工工艺、设备和材料供应条件进行模板及支架设计。模板及支撑的强度、刚度及稳定性应满足受力要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]