[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149977":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149977,802,2,"多选题","下列有关索夹安装控制，说法正确是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","安装前必须测定主缆的空缆线形，设计单位确认索夹位置",true,{"key":16,"text":17,"correct":14},"B","在环境温度稳定时对索夹进行放样、定位",{"key":19,"text":20,"correct":14},"C","清除索夹位置处主缆表面的油污及灰尘并应涂防锈漆",{"key":22,"text":23,"correct":24},"D","当索夹在主缆上精确定位后，应立即紧固索夹螺栓即完成安装",false,{"key":26,"text":27,"correct":14},"E","紧固同一索夹螺栓时，各螺栓受力应均匀，并应按三个荷载阶段（即索夹安装时、钢箱梁吊装后、桥面铺装后）对索夹螺栓进行紧固","ABCE","2020教材P465 \u002F 2019教材P466 1）索夹安装前，必须测定主缆的空缆线形，经设计单位确认索夹位置后，方可对索夹进行放样、定位、编号。放样、定位应在环境温度稳定时进行。2）索夹位置处主缆表面的油污及灰尘应清除并涂防锈漆。4）紧固同一索夹螺栓时，各螺栓受力应均匀，并应按三个荷载阶段（即索夹安装时、钢箱梁吊装后、桥面铺装后）对索夹螺栓进行紧固。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]