[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149976":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149976,802,2,"多选题","施工过程中，必须对主梁各个施工阶段的( )等进行检测，并应及时将有关数据反馈给设计单位。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","拉索索力",true,{"key":16,"text":17,"correct":18},"B","主塔线型",false,{"key":20,"text":21,"correct":14},"C","主梁标高",{"key":23,"text":24,"correct":14},"D","塔梁内力",{"key":26,"text":27,"correct":14},"E","塔索位移量","ACDE","2020教材P465 \u002F 2019教材P466 (1) 施工过程中，必须对主梁各个施工阶段的拉索索力、主梁标髙、 塔梁内力以及索塔位移量等进行监测。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]