[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149973":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149973,802,2,"多选题","已批准占用或挖掘城市道路的工程项目，发生()情况应提前办理变更审批手续。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调换作业队",false,{"key":16,"text":17,"correct":18},"B","需要移动位置",true,{"key":20,"text":21,"correct":18},"C","扩大面积",{"key":23,"text":24,"correct":14},"D","增加施工机械",{"key":26,"text":27,"correct":18},"E","延长时间","BCE","2020教材P463 \u002F 2019教材P464 （4）未按照批准的位置、面积、期限占用或者挖掘城市道路，或者需要移动位置、扩大面积、延长时间，未提前办理变更审批手续的，由市政工程行政主管部门或者其他有关部门责令限期改正，可处以2万元以下的罚款；造成损失的，应当依法承担赔偿责任。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]