[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149962,802,2,"多选题","下列选项中，属于验收批验收合格依据有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主控项目的质量经抽样检验合格",true,{"key":16,"text":17,"correct":18},"B","一般项目全数检验合格",false,{"key":20,"text":21,"correct":14},"C","材料的进场验收和复验合格",{"key":23,"text":24,"correct":14},"D","材料的质量保证资料、试验检测资料齐全、正确",{"key":26,"text":27,"correct":14},"E","具有完整的施工操作依据和质量检查记录","ACDE","2020教材P454 \u002F 2019教材P455 （一）质量验收合格的依据1.验收批（1）主控项目的质量经抽样检验合格；（2）一般项目的质量应经抽样检验合格;当采用计数检验时，除有专门要求外，一般项目的合格点率应达到80%及以上，且不合格点的最大偏差值不得大于规定允许偏差值的1.5倍；（3）主要工程材料的进场验收和复验合格，试块、试件检验合格；（4）主要工程材料的质量保证资料以及相关试验检测资料齐全、正确；具有完整的施工操作依据和质量检查记录。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]