[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149956":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149956,802,2,"多选题","以下关于喷锚暗挖法隧道初期支护安全控制要点正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在稳定岩体中可先开挖后支护，支护结构距开挖面不宜大于5m",true,{"key":16,"text":17,"correct":18},"B","在稳定岩体中可先开挖后支护，支护结构距开挖面不宜大于2倍洞径",false,{"key":20,"text":21,"correct":14},"C","初期支护结构完成后，及时填充注浆，注浆滞后开挖面距离不得大于5m",{"key":23,"text":24,"correct":18},"D","初期支护结构完成后，及时填充注浆，注浆滞后开挖面距离不得大于2倍洞径",{"key":26,"text":27,"correct":14},"E","在不稳定岩土体中，支护必须紧跟土方开挖","ACE","2020\u002F2019教材P446 （二）喷射混凝土初期支护：（1）隧道在稳定岩体中可先开挖后支护，支护结构距开挖面不宜大于5m;在不稳定岩土体中，支护必须紧跟土方开挖工序。（2）钢筋格栅拱架就位后，必须支撑稳固，及时按设计要求焊（栓）连接成稳定整体。（3）初期支护应预埋注浆管，结构完成后，及时注浆加固，填充注浆滞后开挖面距离不得大于5m。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]