[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149949,802,2,"多选题","以下有关对盾构施工的安全控制措施的说法中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","拆除洞口临时维护结构前，必须确认洞口土体加固效果",true,{"key":16,"text":17,"correct":14},"B","作好洞口密封，并设置注浆孔，作为洞口防水堵漏的应急措施",{"key":19,"text":20,"correct":21},"C","采取全部压气工法，以防止打开入孔时直至操作人员返回隧道前地下水涌入",false,{"key":23,"text":24,"correct":21},"D","对开挖面前方土体进行加固处理，以确保土体稳定性",{"key":26,"text":27,"correct":21},"E","根据容许变形值确定不同水平的施工管理值与量测监控方案","AB","2020教材P441 \u002F 2019教材P442 （1）拆除洞口临时围护结构前，必须确认洞口土体加固效果，以确保拆除后洞口土体稳定。（2）施做好洞口密封，并设置注浆孔，作为洞口防水堵漏的应急措施，以防止盾构始发期间土砂随地下水从衬砌外围与洞体之间的间隙涌人工作井。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]