[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149945":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149945,802,2,"多选题","拆除桥梁施工不得垂直交叉作业，应采取（ ）等方法进行，以确保结构安全稳定。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","从上至下",true,{"key":16,"text":17,"correct":14},"B","逐层拆除",{"key":19,"text":20,"correct":21},"C","上下同时",false,{"key":23,"text":24,"correct":14},"D","逐层分段",{"key":26,"text":27,"correct":14},"E","先拆除非承重结构，再拆除承重结构","ABDE","2020\u002F2019教材P438 1.（2）当采用机械拆除桥梁时，应从上至下，逐层分段进行；应先拆除非承重结构，再拆除承重结构。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]