[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149937":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149937,802,2,"多选题","箱涵顶进在穿越铁路路基时，在（ ）情况下，可采用低高度施工便梁方法。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","土质条件差",true,{"key":16,"text":17,"correct":18},"B","顶进速度高",false,{"key":20,"text":21,"correct":14},"C","土壤含水量高",{"key":23,"text":24,"correct":14},"D","地基承载力低",{"key":26,"text":27,"correct":14},"E","列车不允许限速","ACDE","2020教材P433 \u002F 2019教材P434 二（一）（3）在土质条件差、地基承载力低、开挖面土壤含水量高，铁路列车不允许限速的情况下，可采用低高度施工便梁方法。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]