[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149931,802,2,"多选题","拆除工程施工过程中，当发生重大险情或生产安全事故时，应及时启动应急预案，采取（ ）等措施，并向有关部门报告。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","疏导交通",false,{"key":16,"text":17,"correct":18},"B","排除险情",true,{"key":20,"text":21,"correct":14},"C","保持信息畅通",{"key":23,"text":24,"correct":18},"D","保护事故现场",{"key":26,"text":27,"correct":18},"E","组织抢救","BDE","2020教材P440 \u002F 2019教材P441 四（10）拆除工程施工过程中，当发生重大险情或生产安全事故时，应及时启动应急预案排除险情、组织抢救、保护事故现场，并向有关部门报告。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]