[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149930":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149930,802,2,"多选题","拆除工程施工中，（ ）等均属于施工必须建立安全技术档案。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工合同及安全管理协议书",true,{"key":16,"text":17,"correct":14},"B","安全专项施工方案",{"key":19,"text":20,"correct":21},"C","进场安全教育与培训",false,{"key":23,"text":24,"correct":14},"D","脚手架及安全防护设施检查验收记录",{"key":26,"text":27,"correct":21},"E","施工技术交底记录","ABD","2020教材P440 \u002F 2019教材P441 四（6）拆除工程施工必须建立安全技术档案，并应包括下列内容：1）拆除工程施工合同及安全管理协议书；2）拆除工程安全施工组织设计或安全专项施工方案；3）安全技术交底；4）脚手架及安全防护设施检查验收记录；5）劳务用工合同及安全管理协议书；6）机械租赁合同及安全管理协议书。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]