[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149924":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149924,802,2,"多选题","风险等级评价方法可采用（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","神经网络分析法",true,{"key":16,"text":17,"correct":18},"B","隐患调查法",false,{"key":20,"text":21,"correct":14},"C","模糊综合评估法",{"key":23,"text":24,"correct":14},"D","贝叶斯网络方法",{"key":26,"text":27,"correct":14},"E","风险矩阵法","ACDE","2020教材P413 \u002F 2019教材P414 风险等级评价方法可采用风险矩阵法，层次分析法，故障树法，模糊综合评估法，蒙特卡罗法，敏感性分析法，贝叶斯网络方法，神经网络分析法",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]