[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149923,802,2,"多选题","当发生下列（ ）情况，项目需要对安全保证计划进行评估。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","适用法律法规和标准发生变化",true,{"key":16,"text":17,"correct":14},"B","项目组织机构发生重大变化",{"key":19,"text":20,"correct":21},"C","劳务队发生变化",false,{"key":23,"text":24,"correct":14},"D","发生生产安全事故",{"key":26,"text":27,"correct":21},"E","设计图纸出现变更，方案进行局部调整","ABD","2020教材P415 \u002F 2019教材P416 （二）发生下列情况时，应及时进行安全生产计划评估；1、适用法律法规和标准发生变化。2、企业、项目部组织机构和体制发生重大变化。3、发生生产安全事故。4、其他影响安全生产的重大变化。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]