[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149909":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149909,802,2,"多选题","柔性管道回填土回填作业的压实遍数，按（ ），经现场确定",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","虚铺厚度",true,{"key":16,"text":17,"correct":14},"B","含水量",{"key":19,"text":20,"correct":21},"C","压实遍数",false,{"key":23,"text":24,"correct":21},"D","压实厚度",{"key":26,"text":27,"correct":14},"E","压实工具","ABE","2020教材P396 \u002F 2019教材P397 （5）管道半径以下回填时应采取防止管道上浮、位移的措施；回填作业每层的压实遍数，按压实度要求、压实工具、虚铺厚度和土的含水量，经现场试验确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]