[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149904":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149904,802,2,"多选题","关于防腐层施工，以下叙述正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","相对湿度较大的环境对施工质量的影响很大",true,{"key":16,"text":17,"correct":14},"B","涂刷类型的防腐层应按规定分层施工",{"key":19,"text":20,"correct":14},"C","胶带类型的防腐层施工时，应严格控制好施工温度，严禁超温加热",{"key":22,"text":23,"correct":24},"D","冰冻期不宜进行室外防腐层施工",false,{"key":26,"text":27,"correct":14},"E","胶带类型的防腐层施工有搭接宽度和施工顺序的要求","ABCE","2020教材P392 \u002F 2019教材P393 五、管道防腐保温质量控制：2、防腐施工：在雨、雪、风沙天气以及相对湿度较大的环境下，应采取有效措施保证防腐施工质量。涂刷类型的防腐层应按规定分层进行，每层涂料施工时，前道涂料应表干，涂层厚度应均匀，无流淌、褶皱、针孔、空鼓等缺陷，实干后方可采取保护措施，胶带类型的防腐层施工时，应严格控制好施工温度，严禁超温加热，搭接宽度应符合标准规定或设计要求，施工顺序应符合生产厂家要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]