[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149898":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149898,802,2,"多选题","在热力管道焊接过程中，施工控制的重点内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","焊接环境",true,{"key":16,"text":17,"correct":14},"B","焊接工艺参数",{"key":19,"text":20,"correct":14},"C","焊接顺序",{"key":22,"text":23,"correct":14},"D","焊后热处理",{"key":25,"text":26,"correct":27},"E","焊后检测修补",false,"ABCD","2020教材P391 \u002F 2019教材P392 （二）焊接过程控制重点：1、焊接环境；2、焊接工艺参数；3、焊接顺序；4、焊接热处理。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]