[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149891":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149891,802,2,"多选题","进出工作井的安全质量控制主要措施有（ ）等。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按照设计要求，采取超前小导管注浆加固措施",true,{"key":16,"text":17,"correct":14},"B","在进出位置安放钢拱架并及时喷射混凝土",{"key":19,"text":20,"correct":14},"C","根据设计给定的暗挖施工步骤，凿除进出位置的工作井支护结构",{"key":22,"text":23,"correct":24},"D","监测数据信息反馈，调整设计和施工参数",false,{"key":26,"text":27,"correct":14},"E","按照设计要求，采取大管棚注浆加固措施","ABCE","2020教材P372 \u002F 2019教材P373 四、安全质量控制主要措施：1、进出工作井：（1）按照设计要求，采取大管棚或者超前小导管注浆加固措施。（2）根据设计给定的暗挖施工步骤，凿除进出位置的工作井支护结构。（3）在进出位置安放钢拱架并及时喷射混凝土。D选项属于减少地面沉降措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]