[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149890":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149890,802,2,"多选题","二衬施工质量控制中，下列表述正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","结构变形基本稳定的条件下施作",true,{"key":16,"text":17,"correct":14},"B","模板支架应预留沉降量",{"key":19,"text":20,"correct":14},"C","应从下向上浇筑，各部位应对称浇筑、振捣密实，且振捣器不得触及防水层",{"key":22,"text":23,"correct":14},"D","拆模时间应根据结构断面形式及混凝土达到的强度确定",{"key":25,"text":26,"correct":27},"E","减水型、缓凝型外加剂，其掺量应按设计要求确定",false,"ABCD","2020教材P371 \u002F 2019教材P373 （二）二次衬砌施工（1）结构变形基本稳定的条件下施作；（2）2）模板支架预留沉降量为：0~30mm；（3）3）应从下向上浇筑，各部位应对称浇筑、振捣密实，且振捣器不得触及防水层；（4）3）减水型、缓凝型外加剂，其掺量应经试验确定；（5）拆模时间应根据结构断面形式及混凝土达到的强度确定；",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]